The range of parties that are now involved in the provision of energy:

  • Distribution Network Operators
  • Meter Operators
  • Local metering operators
  • Inspectors from the utility service providers
  • Utility suppliers
  • Public Gas Transporters
  • Contractors
  • Sub- Contractors
  • Architects

The stages to a successful project:

Stage 1: Application: On average it can take 5 to 8 weeks for service providers to design and provide their quotations. It can take far longer with certain service providers or if insufficient information was initially provided.

Stage 2: Programming: Once the quotation is accepted and your payment to the utility service providers has been processed, there can follow a 12-15 week delay before the service providers commence the required work.

Stage 3: Supply Registration: Oversights and errors regularly occur in the registration of new supplies, which create additional delay.

Stage 4: On-Site Works: The site works and provisions must be completed in the correct order. With so many parties potentially involved one action out of order will expose the project to delay.